The 2026 heating electrification subsidy
The government has made 2026 the first year of a heat pump roll-out: 25,000 units this year, 60,000 next, and 767,000 by 2035. The first target is rural, mountain and island houses without a gas main, replacing kerosene and LPG boilers with heat pumps.
How much is paid
The programme covers 70% of the purchase and installation cost, including ancillaries, split 40% national and 30% local, with a ceiling of 9.8m KRW. Any cost above 14m is the owner's. One district notice allocated 56m KRW for four households, with 22.4m national, 16.8m local and 16.8m owner contribution.
On an 8–10m installation the grant is 5.6–7m and the owner pays 2.4–3m. Against a 1m boiler replacement the extra outlay is 1.4–2m, and a 690,000 KRW annual saving pays it back in two to three years.
| Item | Amount | Note |
|---|---|---|
| Installed cost | 8–10m KRW | Including ancillaries |
| Subsidy | 70%, up to 9.8m | 40% national, 30% local |
| Owner share | 2–3m KRW | Varies by district |
| Existing boiler | 1m KRW | For comparison |
Eligibility
The unit must reach a seasonal COP of 3.3 and come from an approved list. The house must be a detached or small multi-family home, and the owner or household head applies. Space for the outdoor unit and a buffer tank is required.
In 2026 priority goes to houses that have installed, or will install, at least 3 kW of solar. One district notice made that a condition of application. The design intent is to cover the heat pump's electricity with rooftop generation.
How to apply
Check the district notice, consult an approved installer and sign, then wait for approval before any work: installing first forfeits the grant. One district took applications on 14–16 October by visit or post, and closes early when the budget is spent. In 2027 the programme expands nationwide with a budget of 174.6bn KRW.
Granted systems are usually restricted for five years: removing or transferring one can require repayment. National and local money together may be adjusted so the total does not exceed 70%, so the final own contribution is confirmed only in the district's approval.
Budgets by region
The 2026 programme has 37.7bn KRW for 25,000 units, and 2027 has 174.6bn for 60,000. The budget is allocated by region, so identical houses in different districts face different chances. Jeju, Jeonnam and Gyeongnam started first, with nationwide coverage from 2027.
Check local additions as well. One district combined national and county money to 70% with a 9.8m ceiling; others use different rates and caps, so the district notice is the only reliable source.
After installation
Keep the installation confirmation and photographs. Removing or transferring within five years can require repayment, and without the confirmation it is hard to prove eligibility for an exemption. Because the scheme usually removes the old boiler, keep the removal record too.
Record COP and electricity use through the first winter. If performance falls short of the specification, the record is the basis for a warranty claim. Lowering COP to 2.5 in the calculator shows what a weak installation would cost.
Two worked examples
A 9m installation with 70% support leaves 2.7m. Against a 1m boiler the extra is 1.7m, recovered in 2.5 years from a 690,000 saving. A further 10% local grant cuts the owner's share to 1.8m and the payback to 1.2 years.
At 12m the 70% grant is 8.4m, below the 9.8m ceiling, leaving 3.6m. Above 14m the ceiling applies and the owner's share rises, so keeping the quote under 14m is worth negotiating.
The 2026 round began in warm regions such as Jeju, Jeonnam and Gyeongnam, focused on detached houses with solar, and expands nationwide in 2027. Annual notices take precedence.
Questions
Is the 70% open to everyone?
No. Houses without a gas main come first, and houses with at least 3 kW of solar are prioritised. Gas areas are eligible but competitive.
What if the installation exceeds 14m?
The grant is capped at 9.8m, so anything above is paid by the owner. A larger project therefore lowers the effective rate.
Must the old boiler be removed?
The purpose is to replace coal, kerosene or LPG boilers. Most grants require removal; check with the district before planning a hybrid.
Add the grant and see the real payback.
Open the calculatorBasis 2026-11-28. Written against primary tables; revised when a rate changes.